Obsolete structure forces new plans
County to face increased construction costs because jail building cannot be remodeled
County to face increased construction costs because jail building cannot be remodeled
Thu, 06/26/2025 - 4:30am
Several months of planning and anticipation were suddenly undone when members of the Waseca County Board of Commissioners learned there is no cost-effective way to remodel the current county law enforcement center, which houses the county jail and numerous county offices, including the sheriff’s department and emergency management services.
County leaders had hoped to keep construction costs for a usable jail and safe and improved justice offices at less than $20 million by using a combination of remodeling and new construction to the west of the historic county courthouse.
A recent tour by architects and building planners revealed, however, that numerous elements of the current law enforcement center structure, in use since 1970, make it impossible to add necessary between-floor infrastructure to meet modern air handling, plumbing and electrical needs. Costs to create that space, Commissioner Brian Harguth summarized, were equivalent to “putting a $10 patch on a $5 bald tire.”
Ever since a state Department of Corrections (DOC) report in 2022 warned county officials the jail is in danger of being downgraded or even closed, county leaders have been looking at finding workable solutions for two major problems at once. The first is how to comply with DOC requirements regarding the housing and movement of jail inmates–even including the option of downgrading to a short-term “holding facility” and contracting to have inmates kept at facilities in nearby counties.
The other is that county employees who work in “justice” departments are located in scattered and sometimes cramped locations, while the county courtroom, located at the top of a flight of stairs on the third floor of the historic courthouse, has numerous shortcomings in the areas of accessibility and safety.
Planning efforts have been a persistent attempt to balance between what county administrator Michael Johnson has referred to as the “fiscal” and the “philosophical” sides of the issue. Commissioners have seen price tags ranging from $53 million to $17 million for possible construction plans, and saw the lowest-priced option evaporate at their most recent work session.
Despite the unsettling disappointment, commissioners expressed a desire to continue working toward a solution. After 90 minutes of sometimes tense discussion, Johnson was provided with the direction commissioners want to see taken. The request is that county staff speak with planning companies about scaling down some of the previous models, for example reducing the number of jail cells or decreasing the size of various spaces.