Staff effort enables site
Thu, 08/17/2023 - 4:41pm
The 4.5 acre composting site being added to the Waseca County Recycling Center is being built with 87% of the funding coming from a greater Minnesota recycling and composting grant awarded by the Minnesota Pollution Control Agency, according to information shared by county administrator Michael Johnson. Total cost for the construction is somewhat more than $288,000; the county’s share is somewhat under $39,000, an amount already set aside in the department’s budget.
Waseca County engineer Jim Kollar had noted the need for an improved yard waste composting site years ago; the county had previously applied for a construction grant without receiving one. This year’s application was accepted and the county was awarded $250,000, with the condition that the county provide no less than 25% of the cost either in payment or in-kind local match; according to information shared by Kollar at a board meeting in May, the county was able to meet that requirement by providing aggregate to be used in the construction. With that obligation met, the county was left only with paying the difference between the $250,000 grant and the $288,000 construction cost.
Another positive element was that, although Kollar had estimated construction bids might be as high as $495,000, the low bid among the 10 received was for $288,000 from Evans Companies Landscaping of Byron, nearly 42% less than anticipated.
Construction has been underway throughout the summer, with completion anticipated by September 2. The area where yard waste will be delivered and processed is already finished; a holding pond at the southern end is all that remains for Evans Companies to complete.
Administrator Johnson credits the county’s acquisition of the new facility to “a tremendous effort” on the part of staff and notes that the improved facilities will provide important services and benefits for county residents.
Also anticipated are some upgrades on the main grounds of the recycling center facility, according to supervisor Tammie Bramer. These upgrades were already scheduled, and will be helpful as the expansion leads to increased traffic at the center. Those visiting the facility will be asked to use an alternate driveway for a few weeks while the main drive is widened; the large driving and parking area between the recycling center and the compost site will also be repaved.
Around the end of September when all the new services and upgrades are in place, Bramer says she anticipates visits to the center will be smoother and more pleasant.