Well maintenance likely to cost $600,000
Thu, 12/14/2023 - 11:40pm
The Waseca City Council had a light agenda for its first meeting of the month on October 3. Aside from routine “consent agenda” items, three official actions occurred.
The council’s first meeting of November has been moved to Wednesday, Nov. 8. The regular November 7 meeting had to be rescheduled because of the preliminary special election that day to fill the empty seat on the Waseca County Board of Commissioners. State law forbids holding a public meeting overlapping an election.
Council members approved about $7,000 in “nuisance” fees to be assessed against numerous properties located throughout the city. The assessments came about because property owners were not following maintenance requirements, including mowing and trimming of grass and removal of rubbish. According to a summary provided by city finance director Alicia Fischer, property owners were notified that their lots were not complying with city code expectations and given a deadline. When the deadline was not met, the city hired contractors to perform the needed task. In some cases, properties were mowed numerous times, leading to assessments against some properties as high as $700 and $800.
City council members authorized city manager Carl Sonnenberg to send out a request for bids on well maintenance work to be performed in 2024 and 2025 at a cost likely to be above $600,000. Sonnenberg explained the city routinely performs “well rehabilitation” work every 5 to 7 years; the last time it was carried out was in 2019. Prior to that, it took place in 2014.
The rehabilitation involves removing the pumps and equipment at the top of the well and sending them to a qualified company for inspection, maintenance and repair. A camera is sent down the length of the well shaft to confirm the structural integrity of the bore hole.
Sonnenberg shared a 100-some page report which summarized work performed during the 2018-19 rehabilitation, telling council members he wanted them to see how extensive the process is.
The city well system includes five wells, most located along a line south of Loon Lake within a block or two of Old Highway 14; a fifth well is near the Junior Senior High School. Because one of the five belongs to Conagra, the roughly $100,000 for work on well number four will be reimbursed by the corporation. Payment for work on units one, two, three and five will come from city water utility income, Sonnenberg told council members.
Contacted after the meeting, Sonnenberg shared that city wells are all at least 700 feet deep and are capable of delivering up to 1,000 gallons of water a minute. He also explained that work on the wells must be timed carefully to assure the system is always capable of meeting not only typical daily needs, but emergency services as well.
During the October 3 meeting, council members authorized city staff to seek bids for the work: once bids are received, the council will carry out a separate vote to move forward with the rehabilitation.